New Hospital Plan on ‘more stable footing’ thanks to standard designs and central delivery
The government’s reset of its £56 billion New Hospital Programme has put it on a more stable, long-term footing, with its revised plan to standardise hospital construction expected to save costs and to be more attractive to those who have to build them.
That is the conclusion of a review from the National Audit Office, although the auditor warned that this new construction plan, named Hospital 2.0, with a standardised design expected to be launched April must have a stable pipeline of work. It also underlined that the resilience of the wider supply chain remains a risk.
The NAO said:
It is important that the Department of Health and Social Care takes the time needed to get the design for new hospitals right, plans the programme well and then executes the plan efficiently. In particular, the seven schemes to replace hospitals built with RAAC need to be delivered as a matter of priority once a credible plan is in place.
It noted that the issue of slipping schedules was already a live problem as the plan to replace the seven hospitals beset by the problem material RAAC will miss its 2030 deadline:
The construction schedule over the next few years is challenging as schemes adapt to the new approach, and there are risks of delivery dates slipping and construction activity being squeezed into later spending review periods. This could lead to budgetary pressure on later waves of the programme. Close monitoring is needed and scheduling of schemes kept under review.”
One of the remaining concerns, however, is the skills shortage in delivering this huge centralised construction and delivery project, which aims to deliver 41 new hospitals over the next 20 years. The auditor warned that the New Hospitals Programme is currently running with an extremely high vacancy rate of 39% – so has 138 positions to fill.
The auditor reported that the decision to standardise the design and construction of the new hospitals had led to the projects being significantly more accessible to main contractors, with 16 going through a prequalification process – in sharp contrast to four contractors on the previous scheme. The final design of Hospital 2.0 is expected to be delivered in April 2026.
In its list of recommendations, the NAO stressed that DHSC must maintain ‘rigorous oversight’ of the programme to keep it on track and learn lessons between schemes and waves of construction. It also stressed that DHSC needs to allow sufficient time to test that the design is fit for its stated purpose.
It also warned of the risk of undersizing hospitals, if the shift of care from hospital to community does not develop as expected, DHSC could build hospitals that are too small.